FGT Critical Notice

Notice ID: 33357
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Mar 23 2023 1:20PM
Subject: MARCH 2023 --- FGT SUPPLY AREA MAINTENANCE IN ZONE 2 – SECOND UPDATE
Notice Effective Date/Time: Mar 23 2023 1:20PM
Notice End Date/Time: Apr 1 2023 9:00AM
Notice Text:

MARCH 2023 --- FGT SUPPLY AREA MAINTENANCE IN ZONE 2 – SECOND UPDATE

Maintenance that started on February 20, 2023 continues at FGT Compressor Station 8. This maintenance is scheduled to be completed by the end of gas day April 30, 2023. During this maintenance FGT will schedule up to 900,000 MMBtu/day through Station 8. During normal operations FGT schedules up to 1,075,000 MMBtu/day through Station 8.

On March 16, 2023 FGT resumed normal capacity on the East White Lake Lateral scheduling up to 590,000 MMBtu/day on the East White Lake Lateral - Total Lateral Group and up to 420,000 MMBtu/day on the East White Lake Lateral - South Lateral Group. The East White Lake Lateral will now remain at normal capacity through the end of gas day March 31, 2023.