Notice ID: | 40731 |
Notice Type: | Planned Service Outage |
Critical: | Y |
Notice Status Description: | Initiate |
Reqrd Rsp Desc: | No Response Required |
Posting Date/Time: | Nov 28 2023 8:31AM |
Subject: | NOVEMBER-DECEMBER 2023 --- FGT SUPPLY AREA MAINTENANCE IN ZONE 3 – 1ST UPDATE |
Notice Effective Date/Time: | Dec 1 2023 9:00AM |
Notice End Date/Time: | Dec 9 2023 9:00AM |
Notice Text: |
FGT pipeline maintenance continues near FGT Compressor Station 11. This maintenance is to now be completed by the end of gas day December 8, 2023. During this maintenance, FGT will schedule up to 3,000,000 MMBtu/day. During normal operations, FGT schedules up to 3,250,000 MMBtu/day through Station 11. |