FGT Critical Notice

Notice ID: 40731
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Nov 28 2023 8:31AM
Subject: NOVEMBER-DECEMBER 2023 --- FGT SUPPLY AREA MAINTENANCE IN ZONE 3 – 1ST UPDATE
Notice Effective Date/Time: Dec 1 2023 9:00AM
Notice End Date/Time: Dec 9 2023 9:00AM
Notice Text:

FGT pipeline maintenance continues near FGT Compressor Station 11. This maintenance is to now be completed by the end of gas day December 8, 2023. During this maintenance, FGT will schedule up to 3,000,000 MMBtu/day. During normal operations, FGT schedules up to 3,250,000 MMBtu/day through Station 11.