Subject: May 2025 --- FGT WESTERN DIVISION AND MARKET AREA MAINTENANCE - Third Update
Notice Effective Date/Time: May 15 2025 1:16PM
Notice End Date/Time: Jun 1 2025 9:00AM
Notice Text:

FGT will perform maintenance near FGT Compressor Station 4 starting May 16, 2025. This maintenance will probably continue through the end of May 2025. During this maintenance FGT will schedule up to 70,000 MMBtu/day from receipt points west of Station 4 to Rosharon-Brotman (POI 100775). During normal operations, FGT schedules up to 230,000 MMBtu/day through Station 4.

Major receipt and delivery points within the affected area are Union Carbide-Seadrift Delivery (POI 16494), Tres Palacios Storage Receipt and Delivery (POI 78475 and 78476), Gulf Shore Markham (POI 78427), Pledger-Enterprise Receipt (POI 100022), Wilson-Coastal Bend Delivery (POI 100720) and Rosharon-Brotman Delivery (POI 100775). During this maintenance volumes for receipt/delivery points within the affected area must be scheduled from delivery/receipt points within the affected area.

The first major delivery point east of the maintenance area is Attwater-Topaz (POI 100749). The first major receipt point east of the maintenance area is NGPL Jefferson (POI 10240).

FGT continues maintenance at FGT Compressor Station 7. This maintenance will continue through the end of May 2025. During this maintenance FGT may schedule up to 375,000 MMBtu/day through Station 7, During normal operations, FGT schedules up to 465,000 MMBtu/day through Station 7.

FGT has just received new information regarding the recently posted maintenance downstream of FGT Compressor Station 14. That maintenance is no longer required. FGT Compressor Station 14 will remain at normal capacity.