FGT Critical Notice

Notice ID: 53752
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Jun 5 2025 10:41AM
Subject: June 2025 --- FGT SUPPLY AREA MAINTENANCE ZONE 1 AND ZONE 3 -- FIRST UPDATE
Notice Effective Date/Time: Jun 5 2025 10:41AM
Notice End Date/Time: Jul 1 2025 9:00AM
Notice Text:

The FGT maintenance located downstream of FGT Compressor Station 4 is near completion. Normal pipeline operations will resume at the beginning of gas day June 6, 2025. FGT will schedule up to its normal capacity of 230,000 MMBtu/day through Station 4 starting on the gas day of June 6, 2025.

The Pledger-Enterprise Receipt (POI 100022) will also return to its normal capacity of 200,000 MMBtu/day.

FGT continues maintenance at FGT Compressor Station 7. This maintenance is to be completed by the end of gas day June 13, 2025. During this maintenance FGT may schedule up to 375,000 MMBtu/day through Station 7, During normal operations, FGT schedules up to 465,000 MMBtu/day through Station 7.

FGT will be performing maintenance on its FGT Compressor Station 9. This maintenance is scheduled to begin on June 11, 2025, and is to be completed by end of gas day June 11, 2025. During this maintenance FGT will schedule up to 1,075,000 MMBtu/day through Station 9. During normal operations FGT schedules up to 1,250,000 MMBtu/day through Station 9.