Revision (Y/N)
|
Start Date
|
End Date
|
Prev Start
Date
|
Prev End
Date
|
Facility
|
Pooling
Area
|
Zone
|
Maintenance
|
Potential
Impact *
|
N
|
5/2/2023
|
5/7/2023
|
|
|
Delhi Station / MEP Line CP-7
|
Perryville
|
Zone 1
|
Measurement
Station Upgrades
|
1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. No
capacity impact is expected at this time.
|
2. Coordinating with necessary loads.
|
3. Based on historical and current throughput, no
capacity impact is expected. In the event nominations increase
significantly, restrictions may become necessary.
|
4. Coordinating maintenance with interconnecting pipe to
minimize customer impact. No capacity impact is expected at this time;
however, if operating conditions change, affected parties will be notified.
|
5. Affected production notified of shut-in during work.
|
6. Customers may experience pressure fluctuations, but no
capacity impact is anticipated.
|
7. Based upon customer nominations, restrictions may
become necessary.
|
8. Based on all available information, capacity will be
impacted. Capacity reductions will be done in accordance with the provisions
of EGT's tariff regarding scheduling and interruption of services.
|