Revision
(Y/N)
|
Start Date
|
End Date
|
Prev Start
Date
|
Prev End
Date
|
Facility
|
Zone
|
Line
Segment OP Area
|
Maintenance
|
Potential
Impact *
|
OA or News
|
N
|
9/10/2024
|
9/11/2024
|
|
|
Delhi
Station
|
Zone 1
|
South
|
Semi-annual
maintenance
|
8
|
46646
|
N
|
9/11/2024
|
9/11/2024
|
|
|
Line CP
(Panola to Westdale)
|
Zone 1
|
South
|
SCP
Cleaning Pig
|
6
|
N/A
|
N
|
9/12/2024
|
9/12/2024
|
|
|
Line CP
(Westdale to Vernon)
|
Zone 1
|
South
|
SCP
Cleaning Pig
|
6
|
N/A
|
N
|
9/13/2024
|
9/13/2024
|
|
|
Line CP
(Vernon to Delhi)
|
Zone 1
|
South
|
SCP
Cleaning Pig
|
6
|
N/A
|
N
|
9/12/2024
|
9/12/2024
|
|
|
Line CP
(Kinderhawk IC)
|
Zone 1
|
South
|
OPP
Testing
|
8
|
20240808
|
N
|
9/12/2024
|
9/13/2024
|
|
|
Alto
Station
|
Zone 1
|
South
|
Semi-annual
maintenance
|
8
|
46789
|
N
|
9/17/2024
|
9/20/2024
|
|
|
Panola
Station
|
Zone 1
|
South
|
Units 2, 3
- Semi-annual maintenance (one at a time)
|
8
|
N/A
|
N
|
11/5/2024
|
11/9/2024
|
|
|
Vernon
Station
|
Zone 1
|
South
|
Standby
generator and electric starters install
|
8
|
Required
|
N
|
TBD
|
TBD
|
|
|
Gulf Run
(Westdale to DeRidder)
|
Zone 2
|
South
|
Cleaning
pig
|
3
|
N/A
|
N
|
TBD
|
TBD
|
|
|
Gulf Run
(DeRidder to Bienville)
|
Zone 2
|
South
|
Cleaning
pig
|
8
|
Required
|
1. No
capacity impact is expected at this time.
|
|
|
|
|
|
|
2.
Coordinating with necessary loads.
|
|
|
|
|
|
|
|
3. Based on
historical and current throughput, no capacity impact is expected. In the
event nominations increase significantly, restrictions may become necessary.
|
|
|
4. Coordinating
maintenance with interconnecting pipe to minimize customer impact. No
capacity impact is expected at this time; however, if operating conditions
change, affected parties will be notified.
|
5. Affected
production notified of shut-in during work.
|
|
|
|
|
|
|
6. Customers
may experience pressure fluctuations, but no capacity impact is anticipated.
|
|
|
|
|
|
7. Based
upon customer nominations, restrictions may become necessary.
|
|
|
|
|
|
8. Based on
all available information, capacity will be impacted. Capacity reductions
will be done in accordance with the provisions of EGT's tariff regarding
scheduling and interruption of services.
|
|