Start Date
|
End Date
|
Title
|
Location
|
Type of Work
|
Impact
|
SPW
|
10/8/2025
|
10/30/2025
|
2025 GULF RUN ENBRIDGE #1-I/C
|
Midcoast DD to GR
|
Annual Maintenance
|
1
|
|
10/8/2025
|
10/30/2025
|
2025 GULF RUN TENASKA # 1& #2 I/C
|
Enterprise Bulldog
|
Annual Maintenance
|
1
|
|
10/9/2025
|
10/30/2025
|
2025 GULF RUN MARLIN MIDSTREAM #1 I/C SEP. MAINTENANCE
|
Marlin Midstream
|
Annual Maintenance
|
1
|
|
10/10/2025
|
10/30/2025
|
2025 GULF RUN CEGT/ENTERPRISE I/C SEP MAINTENANCE
|
Pipe - Panola
|
Annual Maintenance
|
1
|
|
10/13/2025
|
10/14/2025
|
2025 GULF RUN GEMINI I/C SEP. MAINTENANCE
|
Gemini Panola GR
|
Annual Maintenance
|
1
|
|
10/13/2025
|
10/14/2025
|
2025 GULF RUN PANOLA COMP. STATION SEP. MAINTENANCE
|
Panola Compressor
|
Annual Maintenance
|
1
|
|
10/14/2025
|
10/21/2025
|
Vernon Compressor Fall Maintenance
|
Vernon
|
Annual Maintenance
|
8
|
57945
|
11/10/2025
|
11/15/2025
|
HPL RTU Upgrade
|
HPL
|
RTU Installation
|
8
|
58417
|
|
|
|
|
|
|
|
1. No capacity impact is expected at
this time.
|
2. Coordinating with necessary loads.
|
3. Based on historical and current throughput, no capacity impact is expected. In the event
nominations increase significantly, restrictions may become necessary.
|
4. Coordinating maintenance with
interconnecting pipe to minimize customer
impact. No capacity impact is expected
at this time; however, if operating conditions change, affected parties will
be notified.
|
5. Affected production notified of
shut-in during work.
|
6. Customers may experience pressure
fluctuations, but no capacity impact is anticipated.
|
7. Based upon customer nominations,
restrictions may become necessary.
|
8. Based on all available information,
capacity will be impacted. Capacity
reductions will be done in accordance with the
provisions of GR's tariff regarding scheduling and interruption of services.
|