Updated as of
|
|
2/20/2023
|
|
|
|
|
Listed
below is a summary of the planned outages that could affect capacity or
impact any receipt/delivery locations during the PEPL 2023 outage season.
This schedule is not a complete list of all outages and is subject to change
as the season progresses to reflect any project delays, cancellations or
additions. Additionally, anticipated impact and restrictions are subject to
change.
*All scheduled dates represent gas days as defined in the PEPL Tariff to mean
a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m.
(Central Clock Time).
|
|
|
|
|
|
|
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter(s) Impact
|
03/14/22
|
03/18/22
|
Greensburg
|
200 Line
|
Pipe Replacement
|
No impact to shippers
expected
|
Black Hills Taps may see
reduced pressure, Superior # 41417 will be shut-in
|
03/14/22
|
03/16/22
|
Greensburg
|
100 Line
|
Pipe Replacement
|
No impact to shippers
expected
|
Black Hills Taps may see
reduced pressure, Superior # 41417 will be shut-in
|
04/21/22
|
04/22/22
|
Sooner
|
16" Line
|
Anomaly Dig
|
Capacity through Sooner
Line limited. Meters subject to scheduling reductions.
|
Meters 10632 DCP
Kingfisher & 41433 Enlink Chisholm plt will need to be Shut-in
|
05/13/22
|
05/26/22
|
Liberal
|
200 Line
|
Valve Replacement
|
No impact to shippers
expected
|
Black Hills Farm Taps,
41436, 13240 will be shut-in
|
05/23/22
|
05/27/22
|
Seiling
|
Meter 02428
|
Meter Upgrade
|
No impact to shippers
expected
|
Meter 02428 will be
Shut-in
|
07/06/22
|
08/19/22
|
Glenarm
|
Galesburg 100
|
Hydrotest
|
No impact to shippers
expected
|
Meters 02098 & 02200
to be shut-in
|
07/25/22
|
08/05/22
|
Centralia
|
AP Green Lateral
|
Hydrotest & Tool Run
|
No impact to shippers
expected
|
Meter 02601 will be
shut-in
|
08/15/22
|
08/19/22
|
S. Elk City
|
22" Line
|
Valve Replacement
|
Capacity through South
Elk City Line may be limited. Meters subject to scheduling reductions.
|
Meters 40466 & 12744
will be shut-in
|
8/25/2022
|
8/26/2022
|
Liberal
|
100 Line
|
Valve Replacement
|
No impact to shippers
expected
|
Meter 41409 will be shut-in
|
9/7/2022
|
9/10/2022
|
Sneed
|
200 Line
|
Valve Replacement
|
Flow through a portion of
the Sneed 200 Line will not be available
|
Meters #12724, #41090 will
be shut-in & Meter #13852 may experience higher pressures during this
outage.
|
9/13/2022
|
9/15/2022
|
Tallgrass Grant
|
Meter 09222/09223
|
Meter Upgrades
|
No impact to shippers
expected
|
Meter #09222 & 09223
will be shut-in
|
9/19/2022
|
10/4/2022
|
Sunray
|
100 Line
|
Wireline And Valve Replacement
|
Flow through Sunray Station
will not be available
|
Meters #40524, #06228,
#07430, #09099, #12840, will be shut-in
|
12/7/2022
|
12/7/2022
|
Greensburg
|
100 Line
|
Valve Replacement
|
Meter subject to scheduling reductions.
|
Location: NNATL
|