TW Planned Service Outage

Notice Type Description: Planned Service Outage
Notice Identifier: 111697
Critical Notice Description: Critical notice
Posting Date/Time: Aug 26 2025 9:09AM
Notice Status Description: Initiate
Required Response Indicator Description: No response required
Response Date/Time:
TSP: 7933047
TSP Name: TRANSWESTERN PIPELINE COMPANY, LLC
Subject: Crawford Lateral (Carlsbad, NM) - Pipeline Integrity Maintenance. 9/16/25 through 9/26/25
Notice Effective Date/Time: Sep 16 2025 9:00AM
Notice End Date/Time: Sep 26 2025 8:59AM

Notice Text:

Nominated Volume Affected

August 26, 2025


To: All Transwestern Pipeline Customers

Subject: Crawford Lateral Pipeline Integrity Maintenance


Reason: Cleaning Pigs and ILI Smart tool

Gas Day September 16th, 2025 through September 19th, 2025 (4 days)

Crawford Lateral capacity will be reduced from 170,000 MMBtu/d to 40,000 MMBtu/d.

Crawford Interconnects affected:
POI 100719 - Sendero Crawford 
POI 100727 - Targa Roadrunner


Gas Day September 20th, 2025 through September 22nd, 2025 (3 days)

Crawford Lateral capacity will increase from 40,000 MMBtu/d to 170,000MMBtu/d.

Gas Day September 23rd, 2025 through September 25th, 2025 (3 Days)

Crawford Lateral capacity will decrease from 170,000 MMBtu/d to 40,000MMBtu/d.

Gas Day September 26th, 2025

Crawford Lateral capacity will increase from 40,000 MMBtu/d to 170,000MMBtu/d.



Transwestern reserves the right to revise the above listed schedule. Please continue tomonitorthe Transwestern website for updates and schedule changes.

Reason: Pipeline Maintenance
Location: Crawford Lateral - Located in the Carlsbad, NM area.